For large energy demanding customers (+20 MW) it's natural to connect directly to the regional grid.
Delivery time for the establishment of such grid installations usually takes usually 2 to 5 years from contract. Some points in the regional network have available capacity of 10-20 MW.

Skagerak Nett has more large customers and is familiar with their needs. We are therefore well equipped for new equivalent customers.

Planning and connection takes place in close cooperation between customer and Skagerak Nett. It is important that the customer signals their needs as early as possible to enable Skagerak Nett to plan the development of the grid.